Thanks to grant funds from the Community Resilience Partnership, the Plantation is currently (Spring 2026) working with a team of engineers on a project phase that will result in initial concept designs for future Breakwater resiliency work. This project period consists of a wave modeling study of Monhegan Harbor, draft development of concept designs, and a regulatory review memorandum. This contract period concludes on May 14, 2026, and the final report was delivered to the Plantation on May 11, 2026.
This report includes project background, site conditions, results of the wave modeling study, breakwater concept designs, a regulatory memorandum, and recommendations for future resiliency work. In the Appendix, the engineering team included the presentation of the wave modeling study as well as the detailed concept design drawings. This report is linked below:
Monhegan Breakwater Resiliency Study Technical Report